‌Valve Factory Acceptance Testing

I. Visual Inspection

1. Surface Examination

Casting defects: Cracks/sand holes/laminations

Coating quality: Uniformity (no runs/peeling)

Surface finish: Ra≤3.2μm per ISO 1302

2. Dimensional Verification

Measurement Tools Tolerance
Body OD/Height Digital caliper ±0.5% nominal
Flange bolt hole PCD Coordinate measuring machine ISO 2768-mK

II. Pressure Testing

A. Shell Test (Strength)

Medium‌: Water (compressed air for special valves)

Pressure‌: 1.5×PN (min 0.3MPa)

Duration‌: 5-10 minutes

Acceptance‌: No visible leakage

B. Seat Test (Sealing)

Valve Type Test Medium Pressure Duration
Liquid service Water 1.1×PN 15 min
Gas service Air/Nitrogen 1.1×PN 30 min

Note‌: For double-block-and-bleed valves, perform bidirectional seat tests

Flanged Metal Seated Ball Valve


III. Functional Testing

1. Operation Test

Manual valves‌: ≤10Nm torque (DN≤100)

Actuated valves‌:

Full stroke time ≤30s (pneumatic)

Torque switch calibration per IEC 60534

2. Flow Characteristics

Test equipment‌: Flow coefficient (Cv) test rig

Output‌: Flow vs. opening percentage curve


IV. Leak Detection

1. Helium Mass Spectrometry

Sensitivity: ≤1×10⁻⁹ Pa·m³/s (for vacuum valves)

Methodology:

Pressurize with 5bar He mixture

Scan with detector probe

2. Bubble Test

Immersion duration: ≥2 minutes

Bubble criteria: ≤3 bubbles/min (ISO 5208 Class A)

v type ball valve


V. Material Verification

1. Spectrochemical Analysis

Equipment‌: Optical emission spectrometer

Standard compliance‌:

ASTM A216 (WCB)

ASTM A351 (CF8M)

2. Hardness Testing

Component Method Requirement
Body Brinell HB 187-241 (WCB)
Stem Rockwell HRC ≥35 (17-4PH)