What parameters need to be confirmed when purchasing high-quality carbon steel pipes?
The brand (such as 20#, ST52), size (outer diameter × wall thickness ± tolerance), and delivery status (hot rolling/cold drawing/annealing) must be clearly stated. The technical agreement should indicate the test items (UT/ET/water pressure). For bulk purchases, the original steel mill warranty (MTC) must be checked. For special purposes, the level of non-metallic inclusions (such as ASTM E45) must be agreed upon.
How to inspect the surface quality of steel pipes on site?
Visual inspection shows no defects such as cracks, folds, and scars, and the weld excess height is ≤10% of the wall thickness. Use a micrometer to measure the wall thickness (at least three places at the end and middle of the pipe). The inner wall can be observed for the accumulation of oxide scale with an endoscope. The zinc layer thickness of galvanized pipes is ≥85μm (GB/T 3091). Rusted areas exceeding 5% should be rejected.
What items do third-party testing agencies usually test?
Chemical composition is analyzed by spectral analysis (OES), and mechanical properties are tested by cutting samples for tensile/bending tests. Metallographic testing includes grain size (such as ASTM E112) and decarburization layer depth (≤0.1mm). Corrosion tests include salt spray tests (GB/T 10125). CNAS certified laboratory reports are legally binding.
Why is it necessary to check the material certificate of the steel pipe?
The quality assurance certificate contains key data such as smelting analysis composition, heat treatment curve, and actual mechanical property values. It is necessary to verify the consistency of the steel plant's official seal, standard number (such as GB/T 8163-2018), furnace batch number and steel pipe identification. Imported pipes must provide a Chinese translation of the EN 10204 3.1 certificate. Steel pipes without a quality assurance certificate are prohibited from being used in pressure pipes.
How to protect rights when encountering steel pipe quality problems?
Immediately seal the problematic batch and take photos for record, and send a written objection to the supplier within 15 days. You can apply for SGS or BV third-party re-inspection, and the cost shall be borne by the responsible party. Claim according to the contract terms (usually 1.5 times the value of the goods). Litigation requires the preparation of evidence chains such as purchase contracts, acceptance forms, and test reports. Major quality accidents must be reported to the local market supervision department.