Piling method for large diameter spiral pipe

  • Piling pipe penetration

1) Before construction, the sample piles should be controlled according to the original design drawing, and the sample piles should be reviewed one by one based on the axis, and measurement records should be made. Piling construction can only be carried out after the review is correct. After the pile driving spiral pipe piles are transported to the site, one point of lashing is used for hoisting. When the piles are lifted to the pile position, the piles are inserted. The pile driving spiral pipe piles are aligned with the pile positions released in advance to ensure accurate verticality during penetration. Before piling, a special pile cap must be placed on the pile head, and a hard wooden shock-absorbing pad must be placed on the pile cap. When the pile driving spiral pipe pile is lifted to the pile position for insertion, due to the total dead weight of the pile body and pile cap and the pile hammer When placed on the top of the pile, it will self-sink and penetrate into the soil in large quantities. It will be hammered after it sinks to a stable level;

2) When starting pile driving, the pile driver will drive dry due to the large amount of penetration. When starting the hammering operation, test driving should be done slowly and intermittently until the pile enters a certain depth into the ground. Continuous hammering is not allowed. During the piling process, the verticality of the pile driver guide rod and pile must be corrected at any time, and the pile hammer, pile cap and pile must be kept on the same longitudinal axis;

3) After driving the spiral pipe pile for 1 to 2 meters, the verticality should be recalibrated. When the pile is driven to a certain depth and the pile driving quality is good after review, the hammering should be continued until the hammering is stopped at 60cm to 80cm above the water surface. Connect the piles and repeat the above steps until the design elevation is reached. If the pile position is found to be tilted during the construction process (>1/100L L-steel pile length), the steel pipe pile should be adjusted or pulled out in time and re-constructed;

4) The burial depth of pile driving spiral pipe piles: 10m across the river bed, and the sinking amount within the number of strikes per minute shall not exceed 5mm.

ssaw pipe piles

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  • Connecting piles

The pile body connection of the pile driving spiral pipe pile adopts butt welding on the top and bottom of the pile body. Before welding, the deformed and damaged parts of the lower pile pipe must be repaired. The rust, water or oil sludge and sand at the end of the upper pile pipe must be removed. The welding joint must be polished so that the gap between the upper and lower piles is 2 to 4 mm. At the same time, multi-layer welding is used to weld. After completing each layer of welds, remove the welding slag in time and perform a visual inspection. Each layer of welds should be staggered, and welding blocks should be added around the piles to strengthen the connection between the upper and lower piles. After welding is completed, it must be cooled for more than 5 minutes before hammering and piling.

pipe piles

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  • Welded pile cover

After the construction of the spiral pipe pile is completed, sand is manually poured into the pile to the top of the pile, a pile cover is welded on the top of the steel pipe pile, and 8 to 12 20mm anchoring steel bars are welded on the outer wall.