What are the main processes for manufacturing A333 Gr.10 steel pipe?
A333 Gr.10 seamless steel pipe is typically manufactured using hot rolling or extrusion. The main process begins with a continuously cast round billet or ingot that meets chemical composition requirements. After heating, the billet is punched through a piercing mill to form a hollow shell tube. It is then rolled or extruded through a continuous rolling mill or extruder into a pipe close to the final size. Next, the critical heat treatment step is normalizing, where the pipe is heated to above Ac3 and air-cooled to refine the grain size and optimize performance. Sizing, straightening, and other finishing steps are then performed. Finally, the pipe undergoes rigorous in-line non-destructive testing (such as eddy current or ultrasonic testing), hydrostatic testing, and sample cutting for mechanical and impact testing.

What precautions should be taken when cold bending A333 Gr.10 steel pipe during installation?
Cold bending of A333 Gr.10 steel pipe is possible, but it must be strictly controlled to avoid compromising material properties. The primary consideration is the bend radius. A too small bend radius can lead to excessive thinning or wrinkling of the pipe wall. Generally, the bend radius should be no less than three times the pipe's outer diameter. Appropriate bending dies must be used to ensure uniform force distribution and prevent stress concentration points such as scratches or indentations on the pipe wall surface. After bending, magnetic particle testing (MT) or penetrant testing (PT) is recommended for the bent area to check for microcracks caused by cold work hardening. For large-diameter, thick-walled pipes, localized stress relief may even be considered after cold bending in cold conditions.

What type of welding consumables should be selected when welding A333 Gr.10 steel pipe?

When welding A333 Gr.10 steel pipe, the selected welding consumables must ensure that the weld metal's chemical composition and mechanical properties, especially low-temperature impact toughness, match those of the base material. AWS A5.28 ER80S-Ni3 type welding wire (for TIG/MIG welding) or AWS A5.29 E90C-Ni3 type flux-cored wire (for FCAW) are generally recommended. The deposited metal of these welding consumables also contains approximately 3.5% nickel, ensuring the weld has the same excellent impact toughness as the base material at -100°C. Ordinary carbon steel electrodes (such as E7018) are strictly prohibited for welding. Otherwise, the weld will become the weak link in the low-temperature toughness of the entire pipeline system, making it highly susceptible to brittle fracture.

What preparations are required before welding A333 Gr.10 steel pipe?
Pre-welding preparation is crucial. First, the groove must be machined (e.g., with a beveling machine) or thermally cut (e.g., with plasma). If thermal cutting is used, the oxide layer and heat-affected zone on the groove surface must be ground away. The groove and its inner and outer surfaces, at least 25mm on either side, must be thoroughly cleaned and free of any contaminants, such as oil, rust, and moisture, to prevent porosity and hydrogen-induced cracking. Appropriate preheating is required based on the wall thickness; a preheat temperature of 100-150°C is generally recommended to prevent the rapid cooling of the weld from creating a hard and brittle structure. Welders must hold the appropriate qualification certificates and strictly follow qualified welding procedure specifications (WPS).

Is post-weld heat treatment (PWHT) required after welding A333 Gr.10 steel pipe?
The need for post-weld heat treatment (PWHT) depends primarily on the pipe wall thickness and specific design specifications. For thinner-walled pipes (for example, typically less than 19 mm per ASME B31.3), PWHT is generally not mandatory, as the welding heat input and proper preheating ensure sufficient cooling rates. However, for thicker-walled pipes, PWHT is often required to relieve weld residual stresses, improve the microstructure of the heat-affected zone, and restore toughness. PWHT procedures (such as heating temperature, holding time, and cooling rate) must strictly comply with qualified process specifications, typically heating temperatures between 595°C and 620°C.